You have chosen your pool, discussed it with the pool builder and started to visualize the first swims. Everything seems quite simple: a bulldozer arrives, digs a big hole and the construction can begin. But there is one detail that we don’t always think about: all the earth that comes out of that hole.
For a family pool, this quickly amounts to an impressive amount. Much more than one would imagine looking at a rectangle drawn on a plan. Before starting the work, it is best to know what you will do with these debris.
An 8×4 meter pool does not produce just 48 m³ of earth
The calculation seems easy. Your future pool measures 8 meters long by 4 meters wide, with a depth of 1.50 meters. You multiply the three dimensions and get 48 m³. This is the volume corresponding to these simplified interior dimensions, not necessarily the volume of ground to be excavated.
The excavation must generally be larger than the basin. The thickness of the structure, the working areas, the foundations and any technical requirements must be taken into account.
Let us take a purely illustrative example with an excavation of 8.60 meters long, 4.60 meters wide and 1.70 meters deep. The theoretical volume reaches 67.25 m³ of earth in place. We already have almost 20 cubic meters more than the interior dimensions of the basin. The exact dimensions must obviously come from the professional.
Once it leaves the ground, the earth takes up more space
That is the abundance. When a bulldozer extracts soil, it breaks its compact structure. Air slips between the pieces and the volume increases.
The difference depends on the nature of the terrain. Sand, clay, pebbles or fragmented rock do not react in the same way. Let’s return to our 67.25 m³. With a 25% abundance assumption, this would give approximately 84 m³ of furniture materials To manage. This coefficient is an example of calculation, not a valid forecast for all construction sites.
The actual result must be estimated according to the soil and the materials encountered. That is why a reasonably sized pool on paper can produce quite a lot of work in the garden.
Where to store all this land during the construction work?
Imagine a development garden with a house, a terrace, a shelter and a narrow side access. Once the pool has been dug, there still needs to be enough space for work: the mini-excavator must be able to move around, the workers must have access to the pool, the materials must be delivered and the trucks must be able to maneuver.
If all the earth has been deposited in front of the only available passage, the construction becomes more complicated. Before the first bucket stroke, ask the earthwork contractor to map out the storage areas and circulation routes. The earth must not be piled up along a trench, against a fragile wall, or in a place where its weight could destabilize the ground.
If the garden is difficult to access, read our article on swimming pools installed in gardens that are difficult to access.
Do not mix all the earth into one pile
The surface layer of the garden, often richer in organic matter, is not as interesting as the mineral soil extracted from deeper levels. The first can eventually be reused for landscaping, if its quality allows it. The second can be used for certain arrangements, but it is not necessarily suitable for a vegetable garden.
Ask the landscaper if it is possible to decontaminate and store the soil separately. Avoid mixing it with rubble or construction waste. And watch the weather: very wet soil becomes difficult to move and repeated passage of vehicles can damage the garden.
Our article about Landscaping under the rain address this issue.
Can we keep the land to create our own garden?
Yes, sometimes. On a sloping terrain, part of the rubble can be used to create landscaping features or the fill required in the project. However, the materials must be suitable for this use and the landscaping must comply with local regulations.
You shouldn’t build a terrain of several dozen centimeters without considering the runoff, the stability of the slopes, and the consequences for the neighbors. A decorative mound can be nice; a mountain of earth that sends rainwater towards the neighboring terrace is much less so.
For the backfill near the pool, the requirements depend on the type of basin and the construction system. Do not replace a material prescribed by garden soil without technical validation.
And the land that we don’t keep, where does it go?
The removal of excavated soil is regulated. The soil that leaves its excavation site is subject, according to applicable regulations, to waste management regulations. This does not mean that all soil is contaminated, but it cannot be disposed of anywhere.
The BRGM and the services of the Ministry responsible for the environment present the guides for the off-site valorization of excavated land, updated in September 2024. They distinguish, in particular, the lands derived from potentially polluted sites from other lands, with conditions regarding reuse and traceability.
For a detached house, the most practical solution is often to entrust this organization to the landscaper. Ask him/her about the intended purpose and the appropriate documentation. If any traces of pollution, abnormal odors, or suspicious materials are detected, have the situation evaluated before any normal evacuation.
How many trucks will be needed?
It all depends on the volume and Weight. A bucket may have enough space to hold a certain volume of soil, but it may not reach its maximum load before being filled. For example, wet clay can be heavy.
The number of rotations therefore depends on the nature of the excavations, the vehicle and the access to the site. A narrow gate, a street that is difficult to maneuver or the impossibility of parking near the site can increase the bill.
Do not rely solely on the internal volume of the pool. The landscaper must estimate the volume, the tonnage and the transport constraints.
What needs to be checked on the quote
When comparing two proposals, check that they include the same services. A quote that only lists the price of the excavation may seem attractive. But if the removal is billed separately, the comparison no longer holds true.
Ask for details about the earthwork, loading, transport, handling fees, and any additional work that may be required. Be sure to ask about what happens if the actual quantity exceeds the estimate or if the construction site reveals rock. The distance to the receiving site can also affect the cost.
A clear estimate before work prevents unpleasant discussions when the backhoe is already in the garden.
Before digging, check what is going under the garden
A sewer line, a cable or another buried network may require special precautions. Work near networks is subject, depending on the situation, to the DT and DICT procedures. The fiche Public service on declarations of works near the networks, verified on April 9, 2025, explains the roles of the project manager and the executing company.
Make sure that the necessary procedures are taken care of before the arrival of the machinery. As for urban planning, also check with the town hall for any permits related to your pool: the area, the location of the land and local regulations may change the formalities.
The right approach: plan for the ground to be ready before the bulldozer arrives
Building a swimming pool is not just about the pool itself, its equipment and the future terrace. It is also a project that must operate in a garden that is sometimes already very busy.
By anticipating the volume of excavation, interim storage, re-use possibilities and disposal, you avoid an unexpected expense during the work. And you will finally be able to focus on the subject that really interests you: the pool that will soon take the place of that big hole.